Search
Filters
Close

Celebrate World Corrosion Awareness Day with 20% off eCourses and eBooks with code WCAD2024 at checkout!

Pipeline New Construction Challenges

This paper discusses the many concerns related to new pipeline construction. Including
safety, testing, documentation and lessons learned. Also addressed are aboveground
storage tanks and some of their construction issues.

Product Number: 51317--8947-SG
ISBN: 8947 2017 CP
Author: Eric Langelund
Publication Date: 2017
$0.00
$20.00
$20.00

PIPELINE NEW CONSTRUCTION CHALLENGESKimberly-Joy Harris D.Sc.ENBRIDGE ENERGY COMPANY INC.322 Indianapolis Blvd Suite 202 Schererville IN 46375kimberly.harris@enbridge.comEric S. LangelundPiping & Corrosion Specialties Inc.8371 Jumpers Hole RoadMillersville Maryland 21108ericl@pipingandcorrosion.comABSTRACTWhat does it take to install a new pipeline? Once the right-of-way is acquired and construction has commenced what tasks are required to ensure a safe and successful pipeline installation with effective cathodic protection and AC mitigation?Pipeline installation is accomplished with the efforts of multiple teams of personnel all of whom have their own duties and concerns. Safety transportation materials equipment and construction are some of major parts to the installation of a pipeline. As corrosion engineers we must work in all of these areas to ensure that test lead wires bond cables casing pipes anode groundbeds and rectifiers are all installed and functioning to meet PHMSA/local regulatory agencies and Company time lines and requirements.In addition design considerations must include the pipeline station & AST terminal with regards to coatings piping supports sand for AST bottoms etc… Once a design is approved and construction is underway scheduling with internal departments along with foreign pipelines is critical as existing operations may be interrupted. Commissioning of the system provides additional challenges as extensive planning may be required along with personnel management between OQ and non-OQ tasks.This paper discusses the many concerns related to new pipeline construction. Including safety testing documentation and lessons learned. Also addressed are aboveground storage tanks and some of their construction issues. The topics discussed are practical and the lessons learned are first-hand accounts. The purpose of this paper is to share what has been learned and some of the company policies that have been taken from many years of installing pipelines. Tools to be discussed will cover new technologies & monitoring techniques that are available when dealing with congested and/or limited access pipeline corridors for both AC & DC and when to consider electrical isolation.

 

PIPELINE NEW CONSTRUCTION CHALLENGESKimberly-Joy Harris D.Sc.ENBRIDGE ENERGY COMPANY INC.322 Indianapolis Blvd Suite 202 Schererville IN 46375kimberly.harris@enbridge.comEric S. LangelundPiping & Corrosion Specialties Inc.8371 Jumpers Hole RoadMillersville Maryland 21108ericl@pipingandcorrosion.comABSTRACTWhat does it take to install a new pipeline? Once the right-of-way is acquired and construction has commenced what tasks are required to ensure a safe and successful pipeline installation with effective cathodic protection and AC mitigation?Pipeline installation is accomplished with the efforts of multiple teams of personnel all of whom have their own duties and concerns. Safety transportation materials equipment and construction are some of major parts to the installation of a pipeline. As corrosion engineers we must work in all of these areas to ensure that test lead wires bond cables casing pipes anode groundbeds and rectifiers are all installed and functioning to meet PHMSA/local regulatory agencies and Company time lines and requirements.In addition design considerations must include the pipeline station & AST terminal with regards to coatings piping supports sand for AST bottoms etc… Once a design is approved and construction is underway scheduling with internal departments along with foreign pipelines is critical as existing operations may be interrupted. Commissioning of the system provides additional challenges as extensive planning may be required along with personnel management between OQ and non-OQ tasks.This paper discusses the many concerns related to new pipeline construction. Including safety testing documentation and lessons learned. Also addressed are aboveground storage tanks and some of their construction issues. The topics discussed are practical and the lessons learned are first-hand accounts. The purpose of this paper is to share what has been learned and some of the company policies that have been taken from many years of installing pipelines. Tools to be discussed will cover new technologies & monitoring techniques that are available when dealing with congested and/or limited access pipeline corridors for both AC & DC and when to consider electrical isolation.

 

Also Purchased
Picture for 01627 PIPELINE CORROSION MANAGEMENT
Available for download

01627 PIPELINE CORROSION MANAGEMENT

Product Number: 51300-01627-SG
ISBN: 01627 2001 CP
Author: Jane Dawson, Julia Race, Stephen Peet and Ravi Krishnamurthy
$20.00
Picture for 09045 Pipeline Integrity Restoration
Available for download

09045 Pipeline Integrity Restoration

Product Number: 51300-09045-SG
ISBN: 09045 2009 CP
Author: Mohamed A. Saleem
Publication Date: 2009
$20.00