At December 2007 a leak was observed at second reactor R-4802 collector (2-1/4 Cr - 1 Mo), conveying the effluents to the 3rd furnace F-4803 of Semi-regenerating Platforming unit (Unit 048) of Petit Couronne Refinery – France.

Metallurgical examination shows that cracking was initiated by a localized mechanism known as Creep Type IV at HAZ fine grain zone. Additional constraints produced by rest of refractory blocking also helped with the development of failure.

Actions to avoid small grain size zone were recommended, as to use materials with control of the impurities, use of materials with addition of boron (90 to 130 ppm). Welding procedure was implemented considering pre-heating at 200°C and in terpass temperature up to 250°C and PWHT at 760°C during 1h /inch thickness.

Also inspection actions were taking to assure the quality of repairs and recommendations were implemented in order to modify the design and avoid the blocking of furnace’s tubular elements. Additionally on-site metallurgical examination was included as part of inspection plan.

Key words: Creep Type IV, Furnace, Platforming Unit.
At December 2007 a leak was observed at second reactor R-4802 collector (2-1/4 Cr - 1 Mo), conveying the effluents to the 3rd furnace F-4803 of Semi-regenerating Platforming unit (Unit 048) of Petit Couronne Refinery – France.

Metallurgical examination shows that cracking was initiated by a localized mechanism known as Creep Type IV at HAZ fine grain zone. Additional constraints produced by rest of refractory blocking also helped with the development of failure.

Actions to avoid small grain size zone were recommended, as to use materials with control of the impurities, use of materials with addition of boron (90 to 130 ppm). Welding procedure was implemented considering pre-heating at 200°C and in terpass temperature up to 250°C and PWHT at 760°C during 1h /inch thickness.

Also inspection actions were taking to assure the quality of repairs and recommendations were implemented in order to modify the design and avoid the blocking of furnace’s tubular elements. Additionally on-site metallurgical examination was included as part of inspection plan.

Key words: Creep Type IV, Furnace, Platforming Unit.
Product tags
Also Purchased
Picture for 11151 Research for Creep Damage by Steam Oxidation
Available for download

11151 Research for Creep Damage by Steam Oxidation Scale of 9Cr Boiler Tubes after Long Time Service

Product Number: 51300-11151-SG
ISBN: 2011 11151 CP
Author: Hiroyasu Matsuda, Masahiko Takehara, Koji Kawano, Shigemitsu Kihara, Kouichi Yagi, Daisuke Horikoshi
Publication Date: 2011
$20.00
Picture for 11152 Chromizing of 3-Cr Steel
Available for download

11152 Chromizing of 3-Cr Steel

Product Number: 51300-11152-SG
ISBN: 2011 11152 CP
Author: V Ravi, B Harrison, J Koch, A Ly, A Schissler, B Pint and J Haynes
Publication Date: 2011
$20.00
Picture for 11153 Corrosion and Fouling of Chromium and Nickel Alloys in Petrochemical Environments
Available for download

11153 Corrosion and Fouling of Chromium and Nickel Alloys in Petrochemical Environments

Product Number: 51300-11153-SG
ISBN: 2011 11153 CP
Author: Bill Santos
Publication Date: 2011
$20.00